Silos, Concrete Tower, Foundation/Site Preparation
To price a concrete tower silo completely, three pieces of data are provided. The tank (priced by diameter and height), the unloaded (priced as each), and the foundation/site prep (priced by the diameter of the tank) being built on it. The site prep cost consists of preparing a leveled site for footings appropriate for the diameter of the tank. The foundation consists of a poured concrete footing and poured concrete slab.